TM 10-4930-369-13&P
FIELD MAINTENANCE
MAINTAINER PREVENTIVE MAINTENANCE CHECKS AND SERVICES (PMCS)
INITIAL SETUP:
References
Tools and Special Tools
Inlator Gauge and Hose Assy (WP 0063, Item 4)
Materials/Parts
Equipment Condition
Grease, Automotive and Artillery, 14 oz cartridge
Personnel Required
Quartermaster and Chemical Equipment
Repairer 91J
Table 1. Maintainer PMCS For FDS -- Before.
EQUIPMENT
ITEM TO BE
ITEM
INTERVAL
NOT READY/
CHECKED OR
NO.
PROCEDURE
AVAILABLE IF:
SERVICED
Fuel nozzle lever
1
Fuel Nozzle
Before
1.
Ensure fuel nozzle lever (Figure 1, Item
is not working.
2) operates correctly, without binding or
jamming.
2.
Check that quick-disconnect coupler
Quick-
(Figure 1, Item 1) operates correctly on
disconnect
the fuel nozzle.
coupler
damaged or not
working.
Figure 1. Fuel Nozzle.
3.
Check fuel nozzle does not leak.
Nozzle does not
work or leaks.
00211