0005
TM 10-4930-369-13&P
2.
If no ilter cartridge is present, install a ilter cartridge (WP 0015). If a ilter cartridge is present, raise the
shell to the ilter head and secure with four knobs.
CAUTION
The area must be free of any sharp objects that may puncture the Spill Containment System
(SCS) loor. Failure to comply may cause equipment damage.
NOTE
The following instructions are for the Type III, 6-foot by 12-foot by 1-foot Spill Containment
System (SCS). If the SCS is not available then construct an earthen berm per FM 10-67-1.
3.
Clear and level an area 10 feet by 16 feet, within 25 feet of the equipment to be fueled by the FDS and within
50 feet of the fuel source (tank, drum, etc.), that will feed the FDS. Refer to FM 10-67-1 as necessary. Ensure
the area is free of any sharp objects that may puncture the SCS loor.
4.
Position the SCS in the center of the cleared area.
5.
Unfold the SCS, with folded walls topside (Figure 3).
Figure 3.
SCS Unfolded.
NOTE
If necessary, the tip of the long leg of each wall support should be lubricated with a small
amount of technical petrolatum, to aid in insertion of the wall support into the wall pocket.
6.
Insert 15 wall supports in the pockets of 2 long wall sections and one short wall section. Ensure the support s
long leg (Figure 4, Item 1) is positioned in the wall pockets (Figure 4, Item 2).
00053