3-24.2
Installation . - Cont'd.
g.
Connect elbows (16) to tanks (12).
h.
Connect 4-inch valve assemblies (7) to 4-inch Y assemblies (4).
i.
Install 4-inch suction hose (3) between elbows(16) and 4-inch Y assemblies (4).
j.
Connect reducers (2) to 4-inch tee assemblies (6). Connect coupling adapters (1) to reducers.
k.
Install remaining 4-inch discharge hoses (11 and 17) as shown.
I.
Inspect all connections for correct installation of flanges, coupling gaskets, and clamps and security of all cam-
lock devices.
3-25 Assemble and Install Tanker Truck Receipt Manifold Hoselines, Valves and Fittings .
There (3) manifolds per TPT.
The tee assembly utilized in the tanker truck receipt manifold is crated in a partially assembled condition to facilitate
packaging and shipping. Some assembly is required to place the unit in operating condition prior to installation.
NOTE
The tanker truck receipt manifolds should be installed only under the direction of operations
management.
3-25.1
Assembly. Refer to figure 2-40.
a.
Position crates containing 6-inch tee assemblies near their respective installation sites as indicated in figure 2-67.
b.
Remove 6-inch tee assemblies from crates.
c.
Remove coupling clamps (8, figure 2-40) connecting flanged adapters (1) to tee fitting (9).
d.
Slide one 6-inch coupling gasket over each tee fitting (9) flange.
e.
Align mating surfaces of adapter (8) and tee fitting (9). Pull coupling gasket over sealing surfaces of both pieces.
Ensure gasket is correctly positioned over full circumference of sealing surfaces. Position coupling clamp (8) over
gasket.
f.
While maintaining alignment of mating parts, lock coupling clamp securely.
g.
Repeat steps b. thru d. for other branch of tee fitting (9).
3-21
|