3-25.2 Installation . Refer to figure 2-67.
CAUTION
INTERNAL CLEANLINESS
Make sure all hoselines, fittings and valves are clean internally. Foreign materials may disrupt
operations and damage equipment.
a.
Position crates containing tanker truck receipt manifold components in their respective installation positions as
shown.
b.
Remove components from crates as required.
c.
Check position 600 Gpm hoseline pump (10) installed under paragraph 3-14.
d.
Connect 6-inch tee assembly (1) to discharge side of pump (10). Connect 6-inch suction hose (2) to suction side
of pump.
e.
Position and connect three remaining tee assemblies(1). Install connecting 6-inch suction hoses (2) and 6-inch
discharge hose (9) from pump (10).
f.
Connect coupling adapters (4) to tee fittings (3).
g.
Connect tee assembly (1) to tees (3) with 6-inch suction hoses (2).
h.
Connect 4-inch suction hoses (5) to coupling adapters (4).
i.
Connect 4-inch ball valves (6) and reducers (7) to 4-inch suction hoses (5).
j.
Install 6-inch caps (8) on tee fittings(3).
k.
Connect 6-inch discharge hose (11) from tee assembly (1) to switching manifold.
3-26 Install Sampling Assembly
One (1) per TPT
3-26.1
Install sampling assembly in the location specified in the technical manuals for specific sites or as directed by
operations management.
3-26.2
For information on the sampling assembly, see para. 2-4.8 and Fig. 2-22. Nose para.'s 3-7.1 and 3-7.2.
CAUTION
Ground assembly at time of installation.
3-27 Install Fire Suppression Equipment
3-27.1
Check out, service, install the fire suppression equipment in accordance with overpacked instructional
manuals and specific instruction of operating management. The