3-23.2
Installation.- Cont'd . Refer to figure 2-65.
g.
Connect 4-inch suction hoses (6) to suction side of 350 GPM transfer pump (7) and 4-inch gate valves (12).
h.
Connect 4-inch discharge hoses (8) to discharge side of transfer pump (7).
i.
Connect 4-inch reducer (9) and 3 in gate valve (10) to discharge hose (8).
j.
Inspect all connections to verify correct installation of flanges, coupling gaskets, and clamps and security of cam-
lock fasteners.
3-24 Assemble and Install Optional Tank Configuration Hoselines, Valves and Fittings .
One (1) system per TPT.
NOTE
The optional tank configuration should be installed only if required by operations
management.
3-24.1
Assembly. No assembly of the optional tank configuration is required prior to installation.
3-24.2 Installation. Refer to figure 2-66.
CAUTION
INTERNAL CLEANLINESS
Make sure all hoselines, fittings and valves are clean internally. Foreign materials may disrupt
operations and damage equipment.
NOTE
Elbows (15 and 16) and 4-inch valve assembly (7) are overpacked with the 50,000 gallon tanks
(12).
a.
Connect elbows (15) to inlet ports of 50,000 gallon tanks (12).
b.
Connect 4-inch valve assemblies (7) to Y assemblies (4).
c.
Connect 4-inch discharge hoses (11 and 13) between 4-inch valve assemblies (7) and tank elbows (15). Ensure
the correct hose lengths are installed in the positions shown. Make sure the correct bend radii are maintained.
d.
Connect 4-inch discharge hoses(10 and 11) to 4-inch tee assembly (9), then to Y assemblies (4).
e.
Connect 4-inch hoses (from hoseline outfit) from 4-inch tee assemblies (9) to 4-inch tee assembly (6).
f.
Connect reducer (2) and coupling adapter (1) to tee assembly (6).