3-18.2
Installation. - Cont'd . Refer to figure 2-60A.
b.
Place crates containing hose and fittings in their respective installation position.
c.
Uncrate 6-inch discharge hose assemblies (2 and 6) and position as shown.
NOTE
6-inch suction hoses (8), 6-inch gate valves (9) and elbows (10 and 11) are overpacked with
the 5,000 BBL tank.
d.
Remove protective caps and connect 6-inch suction hoses (8) to tank elbows (11) and gate valves (9) with
coupling gaskets and clamps.
e.
Connect coupling adapters (5) to gate valves (9).
f.
Connect 6-inch suction hoses (6) between gate valves (9) and cross assembly (3).
g.
Connect 6-inch suction hoses (6) to cross assembly (6) and inlet side of pump assemblies (7).
h.
Connect 6-inch discharge hoses (2) between outlet side of pump assemblies (7) and cross assembly (3).
i.
Connect coupling adapters (4) to tank elbows (10).
j.
Connect 6-inch discharge hoses (2) between coupling adapters (4) and cross assembly (3).
k.
Connect 6-inch discharge hoses (2) between cross assemblies (3) as shown.
I.
Inspect all connections to verify correct installation of coupling clamps, coupling gaskets and security of cam-lock
devices.
3-19 Assemble and Install Secondary Module Hoselines, Valves and Fittings .
Two (2) systems per fuel unit/six (6) per TPT.
Assemblies of the secondary module are crated in a partially, assembled condition to facilitate packaging and shipping.
Some assembly is required to place the units in operating condition prior to installation.
a.
Position crates containing 6-inch cross and Y assemblies near their respective installation sites as indicated in
figure 2-61 A.
b.
Remove 6-inch aluminum cross assembly (3), 6-inch aluminum Y assemblies (8), and coupling gaskets from
crates.
c.
Inspect all items for damage, cleanliness, and quantities required.
d.
Remove coupling clamps (3, figure 2-38) connecting flanged adapter (1) to cross (10).
3-13
|