3-15 Install 1250 Gpm Flood and Transfer Pump (Reference Only)
Number and usage varies with specific area.
3-15.1
If called for on specific site TPT operation plan, install, service and prepare for operation in accordance with
the technical manual published by Peabody Barnes, Inc. for their Model US612-ACD.
3-15.2
For general information, see para. 2-4.5 in this manual. Locate as instructed in the field. Note para.'s 3-7.1
and 3-7.2
3-15.3
Approximate erection weight 3000 Ibs.
WARNING
Observe all warnings and cautions noted in the Peabody Barnes Inc. technical manual for
this pump.
Ground equipment at time of installation.
3-16 Install Meter Strainer Assemblies
Three (3) per fuel unit supply line
Three (3) per fuel dispensing set
One (1) per common header to associated pipeline system
Seven (7) per TPT
3-16.1
Install at locations shown on Fig.'s 2-62, 2-63A and 2-638. Note para.'s 3-7.1 and 3-7.2. General information
on unit is in para. 2-4.6 and Fig. 2-19.
3-16.2
Service and prepare for operation in accordance with the manufacturer's manuals overpacked with the
equipment.
3-16.3
Approximateweight500 lbs.
CAUTION
Ground equipment at time of installation.
3-17 Install Filter-Separators
Two (2) per fuel dispensing assembly/six (6) per 1TPT
3-17.1
Install, service, and prepare for operation in accordance with Department of the Army Technical Manual TM
5-4330-211-12.
3-17.2
For general information and location, refer to para.'s 2-4.7 and Fig. 2-20. Note para.'s 3-7.1 and 3-7.2.
3-11
|