TM 10-5430-239-12&P
0016 00
INSTALLATION INSTRUCTIONS
Refer to WP 0005 00.
PRELIMINARY SERVICING OF EQUIPMENT
No preliminary servicing or adjustment is required.
PRELIMINARY CHECKS AND ADJUSTMENT OF EQUIPMENT
Pre-assembly Inspection
1. To make sure the tank has not been damaged during shipment, conduct an inspection before
assembly. Unpack the consolidation box and check to see if all components are present.
2. Check that each female coupling has a sealing gasket. Replace all missing gaskets.
3. Check cam arm operation of all female couplings. Do not use couplings with broken, bent or faulty
cam arms.
4. Check that the gate valves open and close.
5. Check tank for punctures or tears.
END OF WORK PACKAGE