TM 9-2330-398-24
3-24.
GOVERNOR LINKAGE ASSEMBLY REPAIR (continued).
3.
Remove two nuts (10) and governor linkage assembly (7) from fuel metering pump (12) and governor arm (11).
b.
DISSASSEMBLY
Remove two ball joints (9) and nuts (8) from governor linkage assembly (7).
c.
INSPECTION
1.
Inspect governor linkage components for damaged threads, bent linkage rod, defective spring, and excessive wear.
Replace damaged components as required.
2.
Inspect ball joints for tightness. Replace ball joints if they are worn and come apart easily.
d.
ASSEMBLY
NOTE
If new ball joints are used on linkage, position them to obtain the same length or 1/32 inch more than the
old linkage (one turn equals 1/32 inch). If old linkage length is not available, position new ball joints about
midway on each end of linkage, then lengthen 1/8 inch.
Install two ball joints (9) and two nuts (8) on governor linkage assembly (7).
e.
INSTALLATION
1.
Install governor linkage assembly (7) on fuel metering pump (12) and governor arm (11) with two nuts (10).