3-21.2
Installation . Refer to figure 2-638.
CAUTION
INTERNAL CLEANLINESS
Make sure all hoselines, fittings and valves are clean internally. Foreign materials may disrupt
operations and damage equipment.
a.
Position meter strainer (4), cross assemblies (3), and Y assembly near their respective installation points as
indicated.
b.
Connect discharge hose (1) between 6-inch gate valve of switching manifold and inlet side of meter strainer (4).
c.
Connect discharge hose (1) (quantity as required) between outlet port of meter strainer (4) and cross assembly
(3).
d.
Connect discharge hose (1) (quantity as required) between two cross assemblies (3).
e.
Connect discharge hose (1) between cross assembly (3) and primary module cross assembly.
f.
Connect discharge hose (10) between gate valve of return manifold and Y assembly (2).
g.
Inspect all connections to verify correct installation flange, coupling gaskets, and clamps and security of cam-
lock devices.
3-22 Assembly and Install Fuel Dispensing Assemblies .
One (1) system per fuel unit/three (3) per TPT.
3-22.1
Assembly. No assembly of the fuel dispensing set is required prior to installation.
3-22.2
Installation. Refer to figure 2-64.
CAUTION
INTERNAL CLEANLINESS
Make sure all hoselines, fittings and valves are clean internally. Foreign materials may disrupt
operations and damage equipment.
a.
Check position of 350 gpm filter separators (8) and 800 gpm meter strainer (29), installed per paragraphs 3-16
and 3-17.
b.
Connect 4-inch coupling adapters (27) and 4-inch gate valves (6) to inlet side of filter separators (8).
c.
Connect 4-inch coupling adapters (25), water detection kit adapters (11) and 4inch gate valves (6) to outlet side
of filter separators (8).
3-17
|