TM 10-4930-247-13&P
2-12.
OPERATING PROCEDURES-cont.
Refueling Mode
(1)
Connect fuel nozzle to aircraft refueling adapter. Refer to para 2-12b, 2-12c, 2-12d, or 2-12e as applicable
for type nozzle in use.
(2)
Verify that all valves between HEMTT tanker and fuel nozzle are open.
(3)
Start and operate HEMTT tanker. Refer to TM 9-2320-279-10-1.
(4)
When aircraft fuel tank is full, disconnect fuel nozzle from aircraft adapter. Refer to para 2-12b, 2-12c,
2-12d, or 2-12e as applicable for the type nozzle in use.
Recirculation Mode
NOTE
One recirculation nozzle is supplied with the HTARS. To recirculate the entire
system, recirculation procedure must be performed for each refueling point.
(5)
Connect recirculation nozzle to refueling point (CCR nozzle). Refer to para 2-12d.
(6)
Reposition hoses as required to reach HEMTT tanker.
(7)
Connect recirculation nozzle to HEMTT tanker recirculation adapter. Refer to para 2-12d.
(8)
Start and operate HEMTT tanker. Refer to TM 9-2320-279-10-1.
(9)
When recirculation operation is complete, disconnect recirculation nozzle from HEMTT tanker recirculation
adapter. Refer to para 2-12d.
g.
Fuel System Shutdown. Shut down HEMTT tanker in accordance TM 9-2320-279-10-1.
2-40
|