TM 10-4930-238-12&P
Section VI. PREPARATION FOR STORAGE OR SHIPMENT
Place nozzle end of closed circuit nozzle in a suitable container and drain fuel
from system. Drain fuel from each hose assembly and fitting into a suitable
container when they are removed. Failure to do so could result in injury to per-
sonnel or equipment.
4-22. PREPARATION FOR STORAGE OR SHIPMENT.
a.
Shut down the pump assembly by slowly moving engine throttle control lever toward stop position to
idle speed. Allow engine to idle for five (5) minutes to allow engine operating temperature to stabilize.
b.
Move throttle control hand lever to extreme right stop position.
c.
Disconnect ground cables and remove nozzles. Remove discharge hose assemblies and drain fuel into
a suitable container. Install dust plugs and dust caps. Stow discharge hose assemblies on their frame assembly.
d.
Remove discharge hose fittings and drain fuel into a suitable container. Install dust plugs and dust caps.
Stow discharge hose fittings in canvas bag located on frame assembly.
e.
Remove suction hose assemblies and fittings. Drain fuel into a suitable container. Install dust plugs
and dust caps. Stow suction hose assemblies in their canvas container. Stow in suction hose assembly container.
f.
Disconnect pumping assembly ground cable.
g.
Disconnect filter/separator ground cable. Remove ground rod and stow on filter/separator frame.
h.
Remove plug from bottom of pumping assembly volute housing and drain fuel into a suitable container.
Install drain plug in bottom of pumping assembly.
i.
Open air vent valve and open drain valve on bottom of filter/ separator and drain fuel into a suitable con-
tainer. Close valves.
4-34
|