TM 10-4320-351-14
6.4.26
Install Starter................................................................................................................................. 6-79
6.4.27
Install Gates, Shroud and Oil Cooler ............................................................................................... 6-79
6.4.28
Install Flexible Coupling Adapter and Guard to Engine ..................................................................... 6-82
6.4.29
Install Engine in Engine Module...................................................................................................... 6-83
6.4.30
Adjust Fuel Injection Pump............................................................................................................. 6-85
6.4.31
Install Casing................................................................................................................................. 6-88
6.1 GENERAL.
The engine maintenance procedures provided in this chapter are presented in disassembly-reassembly order.
Performance of all procedures in sequence will accomplish a total engine overhaul. Maintenance functions not
comprising an overhaul may be performed by selecting the appropriate disassembly procedures and corresponding
assembly procedures.
6.2 REMOVE ENGINE FROM ENGINE MODULE. (Refer to figure 6-1.)
This task consists of:
a. Removal
INITIAL SET-UP:
Tools:
General Safety Requirements:
Plier, Diagonal Cutting
(Appendix B, Section III, Item 3)
WARNING
Wrench, Combination, 7/16"
(Appendix B, Section III, Item 3)
·
Fuels are toxic and flammable. Do not get on
Screwdriver, Cross-Tip, Size 2
person or clothing. Work in well ventilated area.
(Appendix B, Section III, Item 3)
Do not smoke. Ensure equipment is well grounded.
Screwdriver, Flat Blade, 1/4" x 4"
(Appendix B, Section III, Item 3)
Always use four personnel to move or relocate the
Drain Pan
engine module. Use proper physical lifting
(Appendix B, Section III, Item 3)
procedures or use a suitable lifting device or dolly.
Wrench, Combination, 6 mm
Wear safety shoes, gloves and other suitable
(Appendix B, Section III, Item 3)
protective clothing.
Key, Socket Head Screw, 6 mm
(Appendix B, Section III, Item 3)
Materials/Parts Required:
Key, Socket Head Screw, 3 mm
Tags, Electrical (Appendix F, Section II, Item 16)
(Appendix B, Section III, Item 3)
Washer, Lock (Appendix I, Item 69)
Wrench, Combination, 13 mm
(Appendix B, Section III, Item 3)
Equipment Condition:
Wrench, Combination, 17 mm
Engine module removed from pump-engine module
(Appendix B, Section III, Item 3)
(para. 2.4)
a.
Cut and remove tiedown straps (1) from engine fuel supply line and engine fuel return line.
b.
Remove cable loop (2) from PTO end of engine.
c.
Remove screws (3) and nuts (4) from decompression lever (5). Remove lever (5).
d.
Remove cable clamp (6) from fuel flow solenoid wire cable at black start control knob (7).