Item
No.
5
6
T M 1 0 - 3 8 3 5 - 2 1 9 - 14
Table 2-1. Preventive Maintenance Checks and Services (PMCS) (cont).
B - Before Operation
D - During Operation
A - After Operation
B
D
A
Item to be inspected
P r o c e d u re
Pipe Coupling Clamps
a. Remove nuts (11) and bolts (12).
Separate halves (13) and inspect
gasket (14) for cracks, distortion
and damage. Replace gasket (14)
if damaged.
b. Inspect coupling halves (13) for cracks
and distortion. Inspect nuts (11) and
bolts (12) for damage. Replace
damaged items.
Banding Tool
Inspect tool for breaks, cracks or dis-
torted threads. Replace tool if damaged
Equipment is not
ready/available if:
Cracked, damaged or
distorted gaskets.
D a m a g e d c o m p o n e n t s.
Banding tool is broken, or has
cracks or distorted threads
2 -7
|