(4) Once skid has been removed from site area, unfold tank by returning the top layers to their original position.
Tank should now be in the same position as illustrated in Figure 2-6.
(5) Perform steps 1 and m.
2-3.
PREASSEMBLY INSPECTION. To ensure that the tank has not been damaged during shipment, conduct an
inspection before assembly.
a.
Unpack consolidation box and check that all components are present.
b.
Check that each female coupling has a sealing gasket. Replace all missing gaskets. Refer to Chapter 4 of
this manual for replacement.
c.
Check cam arm operation for all female couplings. Do not use couplings with broken, bent, or faulty cam
arms.
d.
Check that the gate valves open and close. Refer to Chapter 4 of this manual for replacement of
gate
valves.
e.
Check tank for punctures or tears.
2-9
|