TM 5-4320-306-24
2-19. REPLACE/REPAIR DISCHARGE MANIFOLD ASSEMBLY AND DISCHARGE ELBOW
This task covers:
a.
Removal
c.
Cleaning/Inspection/
d.
Assembly
b.
Disassembly
Repair
e.
Installation
INITIAL SETUP:
Tools
Equipment
Condition
Shop equipment, automotive maintenance
Para
Condition Description
and repair, common no. 1
Tool kit, general mechanics automotive
2-16
Control panel cover assembly, con-
trol panel assembly, and control
Materials/Parts
panel base plate removed.
Crocus abrasive cloth (Item 1, Appendix C)
2-28
Muffler guard removed.
REMOVAL:
WARNING
Death or serious injury could occur if unauthorized or unnecessary personnel are
in the hoisting area. Permit only personnel actually engaged in the hoisting
operation to be near the unit and hoisting equipment. All instructions for the
hoisting operations must come from one authorized person.
Injury to personnel or damage to equipment could occur from improper hoisting.
Hoist the load slowly to avoid tearing out lifting bail assembly, slipping slings, or
load shift. Do not jerk the load or swing it from side-to-side when hoisting. This
places additional stress on hoisting components which can cause failure and loss
of load. Be sure hoisting equipment is on solid footing and is suitable for the size
of the load. Watch boom angle and overhead clearance when hoisting.
1
Position a suitable lifting device (1) equipped with a spreader bar and slings over discharge manifold assembly
(2).
2
Attach slings around assembly and put tension on slings. Make sure assembly is properly supported. Spread
slings on spreader bar so that slings hang vertically when attached to assembly.
3
Remove remaining six nuts and six lockwashers (3).
NOTE
Two nuts and two lockwashers were removed when the muffler guard was
removed for access.
2-72
|