3-33 Equipment and Line Identification Marking - Cont'd .
3-33.2
It is also recommended that consideration be given to marking hoselines and pipelines with color-coded
bands and direction of flow arrows as described in MIL STD 161 F.
Care must be taken to correct the marking if the service of a marked section of hose is changed.
3-34 Testing Kit
One (1) per TPT
Check out and store in location designated by operating management.
3-35 Area Clean-up
The area must be cleaned up by the installation crew prior to commencing operations.
Remove all construction dregs, obstructions, boxes, etc. Unused materials, hose, fittings, etc., should be stored in a
specific area for future use. All caps, plugs, etc., should be boxed and marked for use in the event the system is
disassembled for shipment.
3-36 Final Inspection
3-36.1
It is important to make a final inspection utilizing a check-off list arranged essentially in the order of this
installation procedure. This should be done by supervisory and management personnel from both the installation and
operating groups.
3-36.2
The points of inspection to be emphasized include but are not limited to:
a.
Integrity and height of tank berms closed berm drain.
b.
Floodlights Location and operability. Grounding.
c.
Proper laydown of fabric collapsible tanks proper connection of appurtenances.
d.
Pumps Serviced, location, operability. Grounded.
e.
Meter-strainers Flow direction. Grounding.
f.
Filter-separators Flow direction, test adapter installed, grounded.
g.
Hoselines, Valves, Fittings. All couplings closed, flanges tight, valve packing glands tight, valves in operable
position and closed. No sharp bends, proper lay on tank tops, sandbags on ends and bend subject to whip adequate
walkways over hose, evidence of damage.
h.
Sampling assembly Operable location and joints tight. Valves closed. Grounded.
i.
Fire suppression equipment Proof of check out, location, marking.
j.
Safety and no smoking signs Readable and in place.
k.
Review pressure test results and proof of corrective action.
3-28
|