3-9
General - Cont'd.
NOTE
VALVE PACKING
Stem packing on valves is normally shipped with the gland nuts not taken up tightly. It is
necessary that the gland be tightened before the valve is put under pressure in test or
operation.
3-9.4 These instructions assume that the equipment and materials have arrived at the site and are spotted in the manner
described in Section III. As a general rule, installation can proceed on the basis of individual single fuel units at a time or
the total TPT at one time.
3-10 Install Floodlight Sets
Two (2) per fuel unit/six (6) per TPT.
3-10.1
Service, install, and prepare the floodlight sets for operation in accordance with Department of the Army
technical manual TM 5-6230-210-13&P.
3-10.2
Refer to para. 2-4. 11 and Fig. 2-25 in this manual for general information on these sets. Locate as
directed in field.
3-10.3
Approximate erection weight 2170 lbs. ea.
WARNING
Observe all safety warnings and cautions noted in TM 5-6230-210-13&P.
WARNING
Ground equipment at time of installation.
NOTE
Installation early in the erection program is necessary to permit safe installation work at night.
3-11 Install 5000 Bbl Fabric Collapsible Tanks
Six (6) per fuel unit/eighteen (18) per TPT.
3-11.1
Service, install on assigned pad, and assemble appurtenances in accordance with the instructions in the
technical manual published by ILC Dover and overpacked with the tanks.
3-11.2
For general information, on these tanks, refer to para.'s 2-3.3, 2-3.5,2-4.1 and the associated illustrations,
Fig.'s 2-10 and 2-11 in this manual. See field plot plan for location.
3-8
|