1-5
General Configuration and Arrangement - Cont'd.
1-5.4
A Tank Farm, Primary Module, consists of two (2) 5000 bbl fabric collapsible tanks, two (2) 600 gpm hoseline
pumps, and the associated hose, valves, and fittings.
1-5.5
A Fuel Dispensing Assembly, including two (2) filter-separators, is tied in to each Fuel Unit.
1-5.6
Each Fuel Unit is connected to the switching manifold through the Transfer Hoseline Assembly. The
switching manifold is tied into the pipeline system and an optional tanker truck receipt manifold when called for.
Discharge hoses from the fuel units, part of the transfer hoseline assembly, normally connect to the associated pipeline
system. The configuration of the switching manifold may vary with site condition and the specific service requirements.
A single switching manifold may connect two or more TPT's under some conditions.
1-5.7
Meter Strainer Assemblies are installed in the intake transfer hoseline and in the hoseline to the fuel
dispensing assembly.
1-5.8
A Sampling Assembly is installed in the header from the associated pipeline system feeding the switching
manifold. The Testing Kit is used to test samples taken.
1-5.9
When required, three Tanker-Truck Receipt Manifolds, utilizing up to three (3) 600 gpm hoseline pumps
available for this purpose can be installed.
1-5.10
An Optional Tank Configuration involving up to six (6)50,000 gallon fabric collapsible tanks can be tied in in
lieu of a 5000 Bbl fabric collapsible tank or as supplemental storage capacity as dictated by specific site conditions and
service requirements.
1-5.11
A Contaminated Fuel Module consisting of two (2) 50,000 gallon fabric collapsible tanks, a 350 gpm transfer
pump, and the associated hose, valves and fittings is normally installed to receive and load out off-specification or slop
fuels received from the associated pipeline.
1-5.12
Spare pumps or pumping capacity for special fuel transfers can be obtained by utilizing the 600 gpm hoseline
pumps covered in para. 1-5.9 above or by utilizing the 1250 gpm flood and transfer pumps normally supplied with the
associated pipeline system.
(NOTE: Six (6) 1250 gpm flood and transfer pumps are supplied for Area 8, NSN 3835-01-182-1977.)
1-5.13
Fire Suppression Set equipment is located throughout the facility.
1-5.14
The Floodlight Sets are set up to supply lighting in the operating areas.
1-5.15
Roadway Crossing Guards are installed wherever necessary to have hose lines cross roadways.
1-5.16
Equipment is normally installed over an expansive area for fire-protection purposes.
A berm or firewall is constructed around each fabric collapsible tank to contain any spills.