TM 10-6630-247-13&P
Section VI. PREPARATION FOR STORAGE OR SHIPMENT
4-17. SECURITY PROCEDURES.
Refer to AR 190-11 or AR 190-13.
4-18. ADMINISTRATIVE STORAGE.
a.
Placement of equipment in administrative storage should be for short periods of time when a
shortage of maintenance effort exists. Items should be mission ready within 24 hours or within
the time factors as determined by the directing authority. During the shortage period,
appropriate maintenance records will be kept.
b.
Before placing equipment in administrative storage, Preventive Maintenance Checks and
Services should be completed, shortcomings and deficiencies should be corrected, and all
modification work orders (MWOs) should be applied.
c.
Storage Site Selection. Inside storage is preferred for items selected for administrative storage.
If inside storage is not available, keep test kit away from corrosive materials, such as saltwater
spray.
.
4-45/(4-46 Blank)
|