TM 10-5430-238-12&P
0021 00
INSTALLATION
1. Align male coupling (13) and new flange gasket (14) on ball valve (11).
2. Install eight nuts (7), new lockwashers (8), washers (9), and screws (10) to male coupling (13) and
ball valve (11). Torque the fastening hardware to 30 in-lbs (3.41Nm).
3. Align female coupling (6) and new flange gasket (12) on ball valve (11).
4. Install eight nuts (7), new lockwashers (8), washers (9), and screws (10) to female coupling (6)
and ball valve (11). Torque the fastening hardware to 30 in-lbs (3.41 Nm).
5. Install new gaskets (5) in female coupling (6) and dust cap (3).
6. Connect chains (1) to key rings (2) and install dust cap (3) and dust plug (4) to female coupling (6)
and male coupling (13).
END OF WORK PACKAGE
0021 00-2
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |