UNIT MAINTENANCE
PREPARATION FOR STORAGE AND SHIPMENT
PREPARATION FOR STORAGE OR SHIPMENT
SECURITY PROCEDURES
Refer to AR 190-1 or AR 190-13.
ADMINISTRATIVE STORAGE
Placement of equipment in administrative storage should be for short periods of time when a shortage of
maintenance effort exists. Items should be in mission readiness within 24 hours or within the time factors
as determined by the directing authority. During the storage period, appropriate maintenance records will
be kept.
Before placing the equipment in administrative storage, current Preventive Maintenance Checks and
Services (PMCS) should be completed, shortcomings and deficiencies should be corrected, and all
Modification Work Orders (MWO) should be applied.
Storage site selection. Inside storage is preferred for items selected for administrative storage. If inside
storage is not available, trucks, vans, conex containers and other containers may be used.
END OF WORK PACKAGE
|