(5) After skid is removed, unroll tank by pushing on roll.
(6) Unfold tank by pulling each row of deployment straps (1) in opposite directions. (See Figure 4-4.)
This will extend the two top folded layers.
Figure 4-4. Deployment
(7 ) (Refer to figure 4-5) Use deployment straps (1) and tank handles (2) to fully unfold tank (3). Tank
should be laying smooth without folds.
(8) Tank (3) should be centered within the deployment site with one drain assembly (4) at low end of
site. Use tank handles (2) to move tank, as necessary (see figure 4-5).
Figure 4-5. Tank fully deployed
4-5
|