TM 10-4930-243-13&P
4-2. SPECIAL TOOLS, TMDE, AND SUPPORT EQUIPMENT.
Refer to the Maintenance Allocation Chart contained in Appendix B for maintenance tasks authorized at unit level and for
the TMDE and support equipment required to perform these tasks.
4-3. REPAIR PARTS.
Repair parts are listed and illustrated in the Appendix C of this technical manual.
Section II. UNIT PREVENTIVE MAINTENANCE CHECKS AND SERVICES
4-4. GENERAL.
To ensure that the CCR Nozzle and Adapter are ready for use at all times, it must be inspected systematically so that
defects may be discovered and corrected before they result in serious damage or equipment failure. The necessary
preventive maintenance services to be performed are accomplished at the operator level. Defects discovered during
operation of the unit should be corrected as soon as possible. All deficiencies and shortcomings will be recorded
together with the corrective actions taken, on DA Form 2404 (Equipment Inspection and Maintenance Worksheet) at the
earliest possible opportunity.
Table 4-1. Unit Preventive Maintenance Checks and Services.
Procedures:
For Readiness Reporting
Item
Item to be
Interval
Check for and have
Equipment is Not
No.
Inspected
Repaired as Necessary
Ready/Available if:
1
Strainer
Every
Check for foreign matter, and holes.
Holes in strainer.
2 weeks
Clean and/or replace as required (para.
4-10).
4-2
|