TM10-4930-239-12&P
Section III. OPERATOR MAINTENANCE PROCEDURES.
3-4. GENERAL. This section contains the maintenance procedures which the Maintenance Allocation Chart authorizes
the operator to perform. If the FSSP still does not operate properly after performing these maintenance procedures,
contact unit maintenance for assistance.
3-5. GENERAL COMPONENT REPLACEMENT. The FSSP comprises a number of separate assembly and
subassembly components. The operator is authorized to replace a number of these separate components if they should
fail. The following components may be replaced (as an assembly) by the FSSP operator if they are found to be defective.
a.
Hose Assemblies.
b.
Valve Assemblies.
c.
Manifold Assemblies.
d.
Tee Assemblies.
e.
Wye Assemblies.
f.
Adapter Assemblies.
g.
Nozzle Assemblies.
h.
Miscellaneous Fittings.
In the event that any of the above components fail, the operator should replace the defective component with a properly
functioning component exactly like the one which has failed. The operator should not attempt to make any repairs on any
components found to be defective. All defective FSSP components must be sent to unit maintenance for repair.
NOTE
No other operator maintenance is authorized. If the FSSP still fails to operate
properly, contact unit maintenance.
3-5/ (3-6 Blank)
|