Section II. SERVICE UPON RECEIPT
Paragraph
Page
4-4
Unpacking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...4-2
4-5
Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...4-2
4-6
Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...4-2
4-4. Unpacking. Carefully remove any blocking, bracing, and unit containers. Remove all plugs and caps for
visual inspection of system components; then replace them on components, hoses and fittings until they are
connected into the system. Check unpacked equipment as follows:
a.
Inspect the equipment for damage incurred during shipment. If the equipment has been damaged, report
the damage on SF 364, Report of Discrepancy.
b. Check the equipment against the packing slip to see if the shipment incomplete. Report all discrepancies
in accordance with the instructions of DA PAM 738-750.
c. Check to see whether the equipment has been modified.
4-5. Inspection. The following describes the procedure for inspecting the fuel system upon initial receipt.
a. Perform preventive maintenance checks and services (para. 4-8).
b. Inspect equipment for damage and/or missing parts. Carefully inspect hose assemblies for damaged
couplings and inspect hoses for cuts and excessive wear. Report any damaged or missing parts on SF 364,
Report of Discrepancy.
c. Check that ground cables are securely fastened to pump assembly and filter/separator assembly. Make
sure that grounding clip and plug at free ends are securely fastened to the ground cable and that the cable is
attached to the nozzle. Inspect all ground cables for broken or damaged condition.
4-6. installation. Refer to paragraph 2-5.
Section III. UNIT PREVENTIVE MAINTENANCE CHECKS AND SERVICES (PMCS)
Paragraph
Page
4-7
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...4-2
4-8
PMCS Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...4-3
4-7. General. To ensure that the fuel system is ready for operation at all times, it must be inspected so that
defects may be discovered and corrected before they result in serious damage or failure. Defects discovered
during operation of the system shall be noted for future correction to be made as soon as operation has ceased.
Stop operation immediately if a deficiency is noted during operation, which would damage the equipment if
operation were continued. If the equipment fails to operate, troubleshoot with the proper equipment. Report any
deficiencies using the proper forms. (See DA PAM 738-750).