2-44. SPEED REDUCER REPLACEMENT.
This task covers:
a. Removal
b. Disassemble
c. Assemble
d. Installation
e. Test
INITIAL SETUP
Tools
Equipment Condition
General Mechanics Tool Kit (App B, Sect III,
200/600 GPM fuel pump removed (Para 2-18)
Item 1)
Speed Reducer Reservoir removed (Para 2-16)
Torque Wrench 0-300 inch-pounds (App B,
Priming Drain Tank removed (Para 2-15)
Sect III, Item 2)
General Safety Instructions
Material/Parts
WARNING
Preformed Packing (App F, Items 13 and 16)
Support speed reducer before removing the last nut
that supports speed reducer. Failure to comply
could result in injury to personnel.
a. REMOVAL. Refer to Figure 2-69.
(1)
Open door (1).
(2)
Disconnect tubes (2, 3, 4 and 5) from adapters (6, 7, 8 and 9) on bottom bulkhead panel (10).
(3)
Remove fifteen bolts (11), nineteen washers (12), four locknuts (13) and bottom bulkhead panel (10).
(4)
Remove nuts (14), flat washers (15) and adapters (6, 7, 8 and 9) from bottom bulkhead panel (10).
2-166
|