TM 10-3835-219-14
(4) Step 4.
(a)
(b)
(c)
(d)
(e)
(f)
(g)
Secure hose in place by installing a pair of retaining brackets (8) one or two folds behind pull board
assembly (9).
Remove pull board assembly (9).
Flake the next 200 feet (60 m) of hose into box, stopping just short of coupling ring (10)
(coupling clamp (10) on model FIHK-100) which joins the two hose sections.
Compress hose into about half of the box, using procedures in step 3 above.
Secure hose with a second pair of retaining brackets (8). Remove pull board assembly.
CAUTION
Coupling ring must be centered in box to prevent hose damage.
Continue flaking hose into box, and compress hose again at about 750 to 800 feet (225 m -240 m)
into (about three-fourths the box length). Remove first pair of retaining brackets (8) and use them to
secure hose. Remove pull board assembly.
Repeat procedure stopping short of leading end of the segment using second pair of retaining
brackets to secure hose. Remove pull board assembly.
(5) Step 5.
(a)
(b)
(c)
(d)
(e)
(f)
Remove two bolts (11) and nuts (12) securing upper and lower pipe coupling clamp halves (13).
Remove pipe coupling clamps halves (13), gasket (14) and pipe cap (15).
Repeat steps (a) and (b) for opposite end of hose. Stow one pipe coupling clamp and two pipe caps
(15) in displacement and evacuation kit.
To prevent contamination couple leading and trailing ends of hose per paragraph 2-6c(3)h.
When hose ends are coupled together (16), install tail gate assembly (17) onto flaking box by
inserting tail gate assembly into cleats (18) on tie bar assembly. Then position tail gate assembly into
cleats (19) of lower frame member, Secure tail gate assembly with latches (20) and stow
breakaway (21).
Remove all retaining brackets (8) and position next empty flaking box on top of full box and continue
packing hoseline.
c. Hoseline Outfit Kits. Return all hoseline components to the kit with which they were supplied and check for
shortage. Repack kits into storage chests in accordance with loading diagram attached to underside of each chest
lid,
d. Loadinq Diaqrams. Tables 2-5, 2-6, and 2-7 (Model ADC-1200), Tables 2-8,2-9, 2-10, 2-11 and 2-12
(Model 1461) and Tables 2-12,1, 2-12.2,2-12.3, 2-12.4, and 2-12.5 (Model FIHK-100) contain loading diagrams
for each storage chest and list the contents of each kit supplied with the hoseline outfit. Kit items must be
packed as diagramed to provide adequate space and tight packing for shipment.