T M 1 0 - 3 8 3 5 - 2 1 9 - 14
(d) Carefully remove lifting sling hooks from flaking box.
(e) Using lifting shackles (6) as attachment points, securely tie flaking boxes to truck to prevent boxes
from slipping during hose laying operations.
(f)
Remove tailgate assembly as follows (figure 2-2):
1
Slide latches (1) from flaking box (2).
2
Lift tailgate assembly (3) up and away from flaking box (2).
N O T E
Retain tailgate for reuse.
Figure 2-2. Removing Tailgate Assembly.
(g) Install breakaway as follows (figure 2-3):
N O T E
Breakaway must fall away automatically during hose laying operation. Do not
secure breakaway too tightly or hose will not pull out of flaking box. Recover and
retain fabric breakaway for reuse.
1
Position fabric breakaway (1) so that holes (2) in breakaway lineup with cleats (3) on tie bar (4).
Leave both ends of hose (5) outside the breakaway.
2
Thread wire (6) provided with breakaway through top and bottom cleats (3). Secure top of wire (6)
to top tie bar (4) by bending. Bottom end of wire will hang unrestrained.
3
Attach remaining two wire lengths exactly as the first.
2 - 1 7
|