TM 10-5430-239-12&P
0005 00
4. Loosen tape that secures crate liner to the crate sides and ends.
5. Remove the remaining lag bolts from the crate sides and ends. Remove crate sides and ends and
place them outside of the site area.
6. Remove consolidation box from skid and place box outside of the site area. Only tank and slings
should remain on the skid.
7. Fold back crate liner and lifting slings. Make sure liner lifting straps and D-rings are laying flat.
The slings and liner will be used for redeployment.
8. Cut the top of the protective bag down the center and peel away bag from the tank.
9. Remove all desiccant bags and materials and place outside of site area.
Skid Placement
NOTE
For model GTA-210KF skip this task.
Make sure the skid is in the proper position before beginning deployment.
It is very difficult to move the tank once it has been deployed.
1. Place the skid (1) containing the tank (2) in the middle of the prepared site.
2. The length of the skid (1) must be parallel to the slope fall line.
1
2
0005 00-4