Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: ASSEMBLY AND PREPARATION FOR USE. - continued
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

TM 10-3835-231-13 4-4. ASSEMBLY AND PREPARATION FOR USE.  - continued b. Plot plan.  The following procedure for field plot plan preparation is recommended. (1) After the site has been selected, a preliminary plot plan should be made that shows all the major equipment and  system  locations,  including  tanks,  pumps,  floodlight  sets,  fire  suppression  equipment,  fuel  dispensing  areas,  tanker truck receipt areas, and the access roads. (2) After  the  primary  cuts  and  fills  have  been  made  so  that  firm  knowledge  of  the  characteristics  of  the  site  is available,  and  before  the  earthwork  on  tank  sites,  berms,  and  roadways  is  started,  the  preliminary  plot  plan  should  be reviewed, corrected as necessary, to a final plot plan on which equipment locations are firm.  Final roadwork, tank pad and berm construction must be based on this final plot plan. c. Site Preparation and earthwork. (1) General  site  preparation.    Final  site  selection  and  subsequently  site  preparation  and  earthwork  must   be based on the plot plan.  Because the site will probably not be ideal, there must be some give and take between the plot plan and site preparation results.  The following procedures are recommended. (a) Cut an access road to the site unless one already exists (b) Site preparation work should be based on a grading plan that minimizes cuts and fills operations even if the plan is roughly prepared in the field.  The plan should be based on actual on-site elevations and survey, observation of obstructions, and knowledge of the types of soils that appear to be present. (c) Stake out the area that must be cleared, marking where the major components will be located.  Cut, grub out, doze, or if necessary, blast out major obstructions, i.e., trees, bush, large rocks and boulders, buildings, etc. (d) It is only necessary to clear and grade the areas where a.  fuel unit will be located, transfer systems installed, roadways built, and loading and unloading facilities installed.  There must be good drainage from the site. (e) To the extent possible, cuts and fills should be planned and executed such that the volume of cut soils roughly  equals  the  required  fill  for  low  spots,  tank  berms,  and  roadways.    Excavation  of  ground  site  for  the  purpose  of forming the required tank berms and roadways can be converted into a reserve water storage bin. (f) In preparing the grading plan and executing the cut and fill, the major equipment, most particularly the 5000 bbl tanks, should be set on virgin or cut soils, if possible, rather than on fill. (g) If  it  is  required  that  tanks  be  located  on  a  filled  area,  the  fill  must  be  compacted  as  it  is  placed. Compacting after a deep fill has little effect. (h) When  extensive  fill  is  required,  the  slopes  must  be  such  as  to  prevent  slides  and  minimize  erosion. As a rule, there should be no slopes greater than 2:1 (approximately 25°) in sandy or loamy soils. (2) Primary  roadways.    Primary  roadways  must  be  fully  compacted,  have  good  drainage,  and  to  the  extent possible,  have  at  least  a  surface  of  gravel  or  crushed  rock.    Each  side  of  the  road  should  have  an  adequate  ditch  to provide  good  drainage.    Drainage  culverts  should  be  placed  as  required.    The  road,  swale,  ditches,  and  drain  culvert requirements  will  vary  with  site  conditions  and  anticipated  rainfall.   Figure  4-1  shows  a  desirable  road  layout  for  a  widely spread TPT.  Figure 4-2 shows a desirable road layout for a close spaced TPT.  Roadways must be constructed to permit ready access to all areas for installation, operation, fuel loading and unloading, and fire fighting. (3) Secondary roadways.  Secondary roadways within the TPT must be provided to allow movement of material handling   equipment,   pumps,   fire   suppression   equipment,   and   maintenance   access.      Under-road   culverts   are   to   be installed  as  necessary.    The  hoseline  suspension  kit  may  also  be  used  to  allow  vehicles  to  drive  under  the  hoseline. Access must be provided to the pumps and each tank berm. 4-6

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business